May Construction Update

May 3, 2021

May Construction Update

May 3, 2021

Lied Place Residences surpassed a long-held milestone last week when construction crews poured columns and walls for Level 21 and Level 22. At a height of 220’ 2”, it is unofficially the second tallest building in Lincoln, now two inches taller than US Bank.

With the next concrete deck pour scheduled early this month,only three more pours will complete the structure. Framing is complete up to Level 17, drywall is finished up to Level 12, and rough-in work is nearing the end on Level 14. Large windows on Levels 14, 15, and 16 are being installed, and crews are placing siding on the south face of the building. Inside the structure, painting is completed up through Level 11.

Lied Place construction crews continue to enclose the building as it gains height, framing and drywalling as they go. This month, they are expected to commence finish work in the lower units, an exciting prospect for future tenants.